Work on Santa Fe Prompts Road Closure on August 20

Monday, August 19 (6:00 a.m. – 4:00 p.m.):  99 Pipeline will be working in the street shoulder area on the east side of Santa Fe Street approximately 800-feet north of Caldwell Avenue to tie a new storm drain lateral into the existing manhole.  The work will be limited to the shoulder area.  All lanes will remain open, but speeds should slow through the construction zone.

Tuesday, August 20 (6:00 a.m. – 4:00 p.m.):  Santa Fe Street will be CLOSED between Caldwell Avenue on the south side and Monte Vista Avenue on the north side.  99 Pipeline and Dunn's Sand, Inc., will be working in the street to construct a new storm drain lateral and pave back the trench across Santa Fe Street. Traffic will be detoured to Ben Maddox and K Avenue to bypass the construction.  This is scheduled to be a one-day full closure and it is anticipated that Santa Fe Street will be fully re-opened to traffic by 4:00 p.m.

( View PDF )